ryanmorrissey I have been trying to find a way to set default columns for the Task view as well with no luck so far.
I'm also having issues getting the various calendars correct. We have the Project for Web Accelerator loaded.
There is the calendar that the project is based in the project details screen, to which I have added the New Zealand public holidays.
Then there are the individual resource calendars for each of the people working on the project which don't pickup the holidays from the base calendar so they need to be reentered again for every resource. I also noticed that most of the resources defaulted to GMT time rather than the regional setting for New Zealand even though that's the setting in our Office365 tenancy?!
Does anyone know how these calendars interact or where I can find documentation on them?