Actual Task Hours "Auto-populating" in Resource Timesheet
Hello! I have a question about tasks that seem to have time actual values "auto-populate" in them on an employee's timesheets. Basically, when looking at a timesheet in Project Online (PWA), what...
- Apr 06, 2024Cleymay300 --
If the project manager opens the enterprise project in Microsoft Project, and then manually enters a % Complete value on a task with resources assigned to it, the software will automatically calculate the Actual Work for each resource assigned to the task. If the PM then publishes the project, the Actual Work will automatically show up on each resource's Timesheet page in PWA. Have you quizzed your PMs to determine whether any of them are doing what I just described? If they are, tell them to stop doing this, as it appears you want all progress to be entered from the Timesheet page in PWA. The only exception for your PMs is that they can manually mark the % Complete value to 100% on only Milestone tasks. Hope this helps.
Apr 05, 2024
Clemay300 --
When Actual Work values appear automatically on the Timesheet page for one or more users, this indicates that the project manager has manually entered Actual Work for those tasks in the Microsoft Project schedule. Otherwise, there should never be Actual Work values that are automatically populated for a user. Would that explain them mystery? Let us know and we will try to help you.
When Actual Work values appear automatically on the Timesheet page for one or more users, this indicates that the project manager has manually entered Actual Work for those tasks in the Microsoft Project schedule. Otherwise, there should never be Actual Work values that are automatically populated for a user. Would that explain them mystery? Let us know and we will try to help you.
- Clemay300Apr 05, 2024Copper Contributor
Thank you for the quick reply!
To clarify, if a project manager manually manipulating the "Actual Work" values for the tasks in questions, where would they have done that?
Looking at the task in the project in question I can add the "Actual Work" field, however, our PMs are not very adventurous in poking around the app, so I do not think they would have added that field and then updated it. Would they be doing these manual edits elsewhere?
- Apr 06, 2024Cleymay300 --
If the project manager opens the enterprise project in Microsoft Project, and then manually enters a % Complete value on a task with resources assigned to it, the software will automatically calculate the Actual Work for each resource assigned to the task. If the PM then publishes the project, the Actual Work will automatically show up on each resource's Timesheet page in PWA. Have you quizzed your PMs to determine whether any of them are doing what I just described? If they are, tell them to stop doing this, as it appears you want all progress to be entered from the Timesheet page in PWA. The only exception for your PMs is that they can manually mark the % Complete value to 100% on only Milestone tasks. Hope this helps.- Clemay300Apr 08, 2024Copper ContributorThis certainly seems like it is most likely the case for what the PMs are encountering. I will check with them and confirm if they are doing what you described above. Thanks again for the information!