Forum Discussion
Constant2250
Feb 04, 2025Copper Contributor
Default scheduling mode Project app
Hi, the default scheduling mode of projects (fixed duration vs fixed effort) used to be configured in the general parameters settings in Power Apps, of the Project app (project for the web). But sinc...
Paul_Mather
Feb 05, 2025MVP
Hello Constant2250 ,
From the Project model driven app, access settings:
Click Parameters on the left Nav then access the record. On that record, click the Related drop down menu:
Then access the Parameter record and update as needed:
Does that help?
Paul
- Constant2250Feb 06, 2025Copper Contributor
Hello Paul, yes, that is where it used to be. But now the areas are empty.
Both for me as a user with permissions, for a global admin and for a completely other tenant (with yet another account). So apparently this is 'by design' hence my question, where did it go?