Forum Discussion
Frosty666
Apr 25, 2024Copper Contributor
Flags for Resources
I have more than 20 group resource on my project, so i need more flags to create a color for each. How can I add more flags?
Ignacio_Martin
Apr 29, 2024Steel Contributor
Hello
If these are Gantt bar styles, you can continue defining colors after the 20 flags, conditional on the fulfillment of 2 flags at a time, for example (Flag1,Flag2=color x); (Flag1,Flag3=color y); ...
But you have to keep in mind that the bar style row that includes a two flag condition must be below the one flag condition.
I hope you find it useful.
Ignacio
If these are Gantt bar styles, you can continue defining colors after the 20 flags, conditional on the fulfillment of 2 flags at a time, for example (Flag1,Flag2=color x); (Flag1,Flag3=color y); ...
But you have to keep in mind that the bar style row that includes a two flag condition must be below the one flag condition.
I hope you find it useful.
Ignacio