Forum Discussion
Chris_Hill
Mar 11, 2025Copper Contributor
Gridline for Project Start Date Shifts When Printing
Hi I have a solid gridline set for Project Start in the gridlines pop-up, which shows correctly at the project start date [Week 1] in the chart area. However when printing, including print previe...
John-project
Mar 11, 2025Silver Contributor
Chris_Hill,
In addition to Ignacio's suggestion, you could also not display the Start Date gridline but use the drawing tool to draw a vertical line at the start date. That will show correctly in the print.
This isn't the first time there have been issues with Gantt Chart format printing so I'm not too surprised. I suggest you submit a request to fix the issue through the Project feedback channel at:
https://feedbackportal.microsoft.com/feedback/forum/40792262-301c-ec11-b6e7-0022481f8472
John
- Chris_HillMar 12, 2025Copper Contributor
Thank you John. Will do. 👍
- John-projectMar 12, 2025Silver Contributor
Chris_Hill,
You're welcome and thanks for the feedback.
John