How to extract the value of RBS in Enterprise Resource in Project Server 2019?
I try to retrieve the value of RBS in Enterprise Resource in Project Server by using C#/ CSOM. Unfortunately, I just got the Resource Name, as for the value of RBS, I always cannot extract any value ...
Mks_1973
Nov 11, 2024Iron Contributor
Custom_000039b78bbe4ceb82c4fa8c0c400284 is indeed the correct internal name for the RBS field. You can verify the exact internal name in the Project Server's Enterprise Custom Fields section.
RBS is typically a hierarchical field with lookup table values, ensure that you're correctly fetching and parsing these values.
There might be cases where the custom field has no value. Add checks to handle such cases.
Revised code for improve reliability:
// Retrieve the Enterprise Resource by ID
var specificRes = projectContext.EnterpriseResources.GetById(new Guid("46914ae8-3c55-488d-a045-4d1a5aaf1e74"));
// Load relevant properties
projectContext.Load(specificRes, r => r.Name, r => r.CustomFields, r => r.CustomFields.IncludeWithDefaultProperties(cf => cf.LookupTable, cf => cf.LookupEntries));
projectContext.ExecuteQuery();
// Locate the RBS custom field by its internal name
var rbsField = specificRes.CustomFields.FirstOrDefault(cf => cf.InternalName == "Custom_000039b78bbe4ceb82c4fa8c0c400284");
// Ensure the field exists and contains lookup entries
if (rbsField != null && rbsField.LookupEntries.Any())
{
// Retrieve the full hierarchical path for RBS
var rbsValue = string.Join(" > ", rbsField.LookupEntries.Select(le => le.FullValue));
Console.WriteLine($"RBS for Resource '{specificRes.Name}': {rbsValue}");
}
else
{
Console.WriteLine($"RBS field is not set or has no lookup entries for Resource '{specificRes.Name}'.");
}
=========================
string.Join = This code concatenates all LookupEntries to show the hierarchical path if there are multiple levels in RBS. Each LookupEntry represents a level in the RBS hierarchy, and FullValue provides the hierarchical value for that level.
the code check if rbsField is null and if LookupEntries contains any data before attempting to retrieve and display it
ExecuteQuery = is called after loading the resource data, and not again after loading cusField. This reduces the chance of unnecessary network calls and potential misalignments in data fetching
Also ensure that the user or application context has the correct permissions to access custom fields, especially hierarchical fields like RBS.
Test your code with resources where you know the expected RBS values to verify if they are being retrieved correctly.
I hope this will fix your issue, but if the RBS field still returns unexpected values, verify that there are no issues with the lookup table configuration on the server side.
Wei-Painter
Nov 14, 2024Copper Contributor
Hi Mks_1973,
// Retrieve the full hierarchical path for RBS
var rbsValue = string.Join(" > ", rbsField.LookupEntries.Select(le => le.FullValue));
I just tried it, and I can indeed get all hierarchical path for RBS. Is there a way to retrieve the RBS information related to a specific user?
Thanks - I am new player so I have a lot of questions
- Mks_1973Nov 14, 2024Iron Contributor
Yes, you can retrieve the RBS (Resource Breakdown Structure) information specific to a user by filtering based on the user’s resource ID or their specific criteria in the query.
Here's how you can get the RBS value for a specific user:// Assuming you have the context and have authenticated
var projectContext = new ProjectContext("https://your-project-server-url/");// Replace with the user's resource ID
Guid resourceId = new Guid("your-specific-resource-id");// Retrieve the specific resource by ID
EnterpriseResource specificResource = projectContext.EnterpriseResources.GetById(resourceId);// Load the resource with custom fields (including RBS)
projectContext.Load(specificResource,
r => r.CustomFields.Include(cf => cf.InternalName, cf => cf.LookupEntries, cf => cf.Value));
projectContext.ExecuteQuery();// Now, retrieve the RBS field
var rbsField = specificResource.CustomFields.FirstOrDefault(cf => cf.InternalName == "Custom_RBS_Field_Internal_Name");// If the RBS field exists, retrieve its full hierarchical path
if (rbsField != null && rbsField.LookupEntries != null)
{
string rbsValue = string.Join(" > ", rbsField.LookupEntries.Select(le => le.FullValue));
Console.WriteLine("RBS for the specified user: " + rbsValue);
}
else
{
Console.WriteLine("RBS information not found for the specified user.");
}
======================
Replace "your-specific-resource-id" with the actual resource ID for the user you're interested in.
Replace "Custom_RBS_Field_Internal_Name" with the actual internal name for the RBS custom field in your Project Server instance.
Check if the resource has an RBS assigned. If rbsField.LookupEntries is null or empty, the user might not have an RBS assigned.- Wei-PainterNov 15, 2024Copper Contributor
Hi Mks_1973,
Thanks. I will give it a try at this first.
- WEISH1195Nov 14, 2024Copper Contributor
Hi Mks_1973,
Thanks once again. I just try the sample code and ran into the error like this: cf.Value >> Error.
Thanks.
- Mks_1973Nov 14, 2024Iron Contributor
This error might happen if Value is not a valid property for the CustomField object in your context.
Through below code you can retrieve the hierarchical RBS path for a specific resource without relying on the cf.Value property:// Assuming you have the context and have authenticated
var projectContext = new ProjectContext("https://your-project-server-url/"); // Update this with your Project Server URL// Replace with the specific user's resource ID
Guid resourceId = new Guid("your-specific-resource-id");// Retrieve the specific resource by ID
EnterpriseResource specificResource = projectContext.EnterpriseResources.GetById(resourceId);// Load the resource with custom fields (including RBS) and ensure lookup entries are included
projectContext.Load(specificResource,
r => r.CustomFields.Include(cf => cf.InternalName, cf => cf.LookupEntries));
projectContext.ExecuteQuery();// Retrieve the RBS field based on its internal name (replace with actual internal name for RBS in your setup)
var rbsField = specificResource.CustomFields.FirstOrDefault(cf => cf.InternalName == "Custom_RBS_Field_Internal_Name");// If the RBS field exists, retrieve its full hierarchical path
if (rbsField != null && rbsField.LookupEntries != null && rbsField.LookupEntries.Count > 0)
{
string rbsValue = string.Join(" > ", rbsField.LookupEntries.Select(le => le.FullValue));
Console.WriteLine("RBS for the specified user: " + rbsValue);
}
else
{
Console.WriteLine("RBS information not found for the specified user.");
}
==================================
Changes in Above:Since cf.Value seems to be causing an error, I omitted it. Instead, we rely solely on LookupEntries to fetch the hierarchical path.
Added rbsField.LookupEntries.Count > 0 to ensure there are entries to process, which should prevent null reference errors.
Update "https://your-project-server-url/" with your Project Server URL.
Update "your-specific-resource-id" with the actual resource ID for the user.
Replace "Custom_RBS_Field_Internal_Name" with the exact internal name for the RBS field in your Project Server.
If the InternalName for the RBS field is unclear, you may need to inspect your custom fields in Project Server to ensure you're referencing the correct internal name.
Please remember that LookupEntries only works if the RBS field uses a lookup table with hierarchical values.