Forum Discussion
Molalenge
Feb 06, 2025Brass Contributor
MS Project 2019 desktop Reporting- Rows
I provide a monthly PMP status report. When I print the status report, I notice a message at the bottom stating, "Only showing 75 items out of 118 rows. The project can only show 75 rows." I have the...
Ignacio_Martin
Feb 06, 2025Steel Contributor
Hello Molalenge
With my 2025 version it seems that the limit is 150 rows.
I have always had this limitation on the number of rows when creating Tables through the Reports option, so I directly use the task tables from the Gantt chart views which do not limit me, even if I have many tasks.
Ignacio