Forum Discussion
Molalenge
Feb 12, 2024Brass Contributor
Ms Project Software Update
Hi, We are planning to update our MS Project 2019 to MS Project 2021-we are interested in enhancing dashboard reports and possibly link MS Project to MS planner. The product review under Microsoft d...
- Feb 12, 2024Molalenge --
As I stated in my previous post, Microsoft Project can only connect to Planner when used with either Project Online or Project Server. There is functionally no difference between the 2019 and 2021 versions. This is because Microsoft spent all of the their development money on Project for the Web, which is a low-end project management tool for small and simple projects. Microsoft DID announce recently that later this year, Project for the Web will be merged into the Planner app. Hope this helps.
Feb 12, 2024
Molalenge -- I am not clear what information you are seeking. There are no planned enhancements for Dashboard reports and there is already a link between enterprise projects and Planner when Microsoft Project is used with Project Online or Project Server. What information are you seeking? Let us know and we will try to help you.
- MolalengeFeb 12, 2024Brass ContributorThank you Dale for your response; my MS Project 2019 does not link with a Planner! What features are in MS Project 2021 (either the online or the web version) compared to MS 2019? Thanks.
- Feb 12, 2024Molalenge --
As I stated in my previous post, Microsoft Project can only connect to Planner when used with either Project Online or Project Server. There is functionally no difference between the 2019 and 2021 versions. This is because Microsoft spent all of the their development money on Project for the Web, which is a low-end project management tool for small and simple projects. Microsoft DID announce recently that later this year, Project for the Web will be merged into the Planner app. Hope this helps.- CarlosMorenoVFeb 12, 2025Copper Contributor
Hi Dale,
I have seen that Microsoft sells now Project 2024 Standard and Professional perpetual licenses. Is there any difference (apart from colors,themes) from this one to 2019 and 2021 versions?? (not online versions). It seems that only changes numbers, is that right?
Thank you for you attention and answer.