Forum Discussion
Adil365
May 04, 2022Copper Contributor
Project for the Web - Project Tasks Custom Fields - Power BI Reporting
Hello, We're able to add custom fields to Project Tasks table in the Project for the Web, which is a great feature. However, according to this documentation (https://support.microsoft.com/en-...
Paul_Mather
May 04, 2022MVP
Hello Adil365 ,
Unfortunately these custom fields you create here:
Are not available for reporting, they are only available in the Project for the web interface.
Paul
- DaveE555Aug 23, 2023Copper Contributor
Paul_Mather I see custom fields reported in the (new) history table with an ID assigned for the custom field - I am now on a mission to find the table which has the Name for that ID. Any further ideas where custom field values are actually stored? Maybe the history table is the real answer.
I'm currently attempting to baseline a plan - my most basic approach will be to extract point-in-time task data to excel and incorporate that in a powerbi model for SPI calculation. Pushing to a custom baseline column may also be desirable for my organisation.
- Kennet_WaspeFeb 28, 2025Copper Contributor
Any luck on this?
- Dave_JorgensenSep 07, 2023Copper ContributorHi Dave - did you ever find the table that maps field name to the ID? On the same hunt myself right now