Forum Discussion
Adil365
May 04, 2022Copper Contributor
Project for the Web - Project Tasks Custom Fields - Power BI Reporting
Hello, We're able to add custom fields to Project Tasks table in the Project for the Web, which is a great feature. However, according to this documentation (https://support.microsoft.com/en-...
DaveE555
Aug 23, 2023Copper Contributor
Paul_Mather I see custom fields reported in the (new) history table with an ID assigned for the custom field - I am now on a mission to find the table which has the Name for that ID. Any further ideas where custom field values are actually stored? Maybe the history table is the real answer.
I'm currently attempting to baseline a plan - my most basic approach will be to extract point-in-time task data to excel and incorporate that in a powerbi model for SPI calculation. Pushing to a custom baseline column may also be desirable for my organisation.
Kennet_Waspe
Feb 28, 2025Copper Contributor
Any luck on this?