Forum Discussion
Gareth_Eldridge
Aug 04, 2022Copper Contributor
Project for the Web, Project Accelerator and Teams
Good Afternoon all, First time poster and great to be here. I am the head of Programmes and Projects for a SME and I have implemented Project for the Web and the Project Accelerator to great ...
AndrewNorris
Sep 12, 2022Brass Contributor
Hi Gareth
You've hit the snag that many of us have also found. There are some features that can only work if they are in the default environment.
Amongst these are:
Add the Project to a Teams channel
Templates
@ mention and conversations in Project tasks
It's very frustrating and isn't made clear enough on the Accelerator GitHub page nor is it made clear in the Roadmap.
There is no workaround.
It's something we have to keep being vocal about as it is creating a two-tier offering but for the same price.
You've hit the snag that many of us have also found. There are some features that can only work if they are in the default environment.
Amongst these are:
Add the Project to a Teams channel
Templates
@ mention and conversations in Project tasks
It's very frustrating and isn't made clear enough on the Accelerator GitHub page nor is it made clear in the Roadmap.
There is no workaround.
It's something we have to keep being vocal about as it is creating a two-tier offering but for the same price.
- SusanMcClementsMay 02, 2023Steel ContributorIs this still true that if you add Project Accelerator to another environment besides the default, you will not be able to add the Project to a Teams channel? I am having a difficult time setting up the Accelerator in another environment and following the steps for creating a custom solution.