Hello Every one,
We have a customer that want to migrate from SFB 2015 to SFB 2019. But we have found the next blockers to start.
1.) Checking requirements we see that SFB 2019 Enterprise...
Nicholas Burkhammer
Microsoft
Aug 12, 2019You should follow the supportability guidelines. DFL/FFL of 2012 is required as per https://docs.microsoft.com/en-us/skypeforbusiness/plan/system-requirements#os-for-domain-controllers.
If you move forward without meeting the requirements, you could run into issues that force you to upgrade the DFL/FFL if no workaround can be found. That would be an extremely stressful experience if something like that did occur.
Also keep in mind that extended support for 2008/R2 as linked from the product lifecycle page directs to https://azure.microsoft.com/en-us/blog/announcing-new-options-for-sql-server-2008-and-windows-server-2008-end-of-support/ which states January 20, 2020.